TECHNICAL
CRANES
LIMITED
 
 Reconditioned Equipment
 New Equipment
 Gantry & Support Structures
 Crane Repairs & Maintenance
 Itowa Radio & Products
 Crane & Components Exports









 

< home

 

Case Studies

Technical Cranes Ltd supplies BBRT – Scotland Craneage for New Facility

Technical Cranes Ltd were awarded the contract of supplying Balfour Beatty Rail Track Systems with new craneage and gantry steelwork for its new Scottish facility. What was formerly Edgar Allens, sited at Bathgate relocated during 2008 to a new facility at South Queensferry.

A total of 1100 linea meters of gantry track was supplied and installed with support haunches throughout 10 different bays on the site, complete with a powerfeed conductor system.

These gantries support a total of 19 cranes ranging from 5 tonne to 20 tonne for a wide range of applications such as foundry use, fabrication and workshop maintenance.

As part of the contract the redundant craneage at Bathgate was taken in part exchange.

The cranes were all fitted with Itowa Winner radio control systems that Technical Cranes Ltd are UK agents for. Ongoing service and maintenance will be handled by A & B Crane and Electrical, a division of Technical Cranes Limited that serves the north east and Scottish boarders.
 


Technical Cranes relocates Bradford Cylinders Lifting Equipment to new facility, which extends to over 6000 square metres. It is a historical move as Bradford Cylinders had been at its original site for over 100 years.

The project involved supplying Bradford Cylinders with a refurbished 10 Tonne SWL Loading Bay Crane and Gantry and installing 4 bays of floor rails for Goliath type cranes totalling a travel length of 250 metres. The cranes are electrically fed by bussbar systems suspended at roof level from the portal steelwork. Nine overhead cranes from the old works at Allerton Road were removed in phases to minimise disruption to Bradford’s production. They were brought back to our Rotherham works to undergo modification and refurbishment.
Each crane had Goliath legs manufactured and where necessary the spans were altered to suit the new rail centres. Each crane was overhauled and any worn parts were replaced.

Inverter control was installed to the long travel motion of each crane to give a slow and controlled start up and slower and safer travel speeds. The cranes were also fitted with a flashing light, Claxton and Itowa overload protection devices. Finally before reinstallation each crane was fully cleaned and painted.

On completion of the commissioning the cranes were issued with a report of through examination and put straight back into production ready for the next 100 years.
 


Technical Cranes Limited help to increase production and efficiency for Trackline International with the introduction of overhead craneage.

The contract involved fitting out the main fabrication bay with a 110 metre long free standing gantry suitable for a safe working load of 20 tonnes complete with a powerfeed system. The cranes installed were fully reconditioned and consisted of a 20 Tonne, 16 Tonne and two 10 Tonne safe working load twin beam cranes with 19 metre spans.

Technical Cranes service also included for the design and installation of the foundation pads for the gantry columns to sit on.


 


 
website design by
 
 
© 2007 Technical Cranes Limited | Holmes Lock Works, Steel Street, Rotherham S61 1DF, UK
Please Read: Privacy Policy and Terms of Use